Switching your core property management software needs a project plan. The vendor sets up the software. Your team has to move the operation. This checklist covers the parts vendors usually leave to you.

Before you sign

  • ☐ List every report your team pulls weekly or monthly, and who uses it.
  • ☐ Write down how each site actually handles leads, renewals, delinquency, and work orders today.
  • ☐ Ask the vendor which of those reports and workflows exist out of the box and which need setup.
  • ☐ Get the full cost: per-unit fees, implementation, add-on modules, payment processing, and exit fees.
  • ☐ Confirm what data the old system will export, in what format, and what it costs to get it.
  • ☐ Check your current contract’s notice period and termination terms.

Before cutover (4 to 8 weeks out)

  • ☐ Name one internal owner for the project. Not the vendor, and not “the team.”
  • ☐ Name a super user at each site or region who learns the system first.
  • ☐ Schedule training by role (leasing, maintenance, accounting, managers) and track who attended.
  • ☐ Write a one-page standard process for each core workflow in the new system.
  • ☐ Map every recurring charge and fee so nothing drops off the ledger.
  • ☐ Build a GL account crosswalk mapping every legacy chart-of-accounts code to its new-system equivalent, reviewed and signed off by accounting before cutover.
  • ☐ Pick a cutover date away from month-end rent collection.
  • ☐ Tell residents what is changing (portal, payment method, login) on a 30/14/3-day cadence: an initial notice 30 to 45 days before cutover, a reminder at 14 days out, and a final reminder 3 days before go-live.

Cutover week

Cutover weekend blackout schedule

These dates are illustrative placeholders. Replace them with your own cutover calendar, built around the same freeze, verify, and open cadence.

DateAction
Day 1 (e.g., the 10th)Freeze and lock the legacy system. No new transactions or edits after this point.
Day 4 (e.g., the 13th)Reconcile data and verify ledgers balance between old and new systems.
Day 6 (e.g., the 15th)Open the new resident portal and go live.
  • ☐ Pull final reports from the old system and save them: rent roll, aged receivables, deposits, open work orders.
  • ☐ Compare the new system’s rent roll and balances to the old one, unit by unit.
  • ☐ Confirm autopay and resident payments are flowing into the right bank account.
  • ☐ Check that websites and listing feeds show correct pricing and availability.
  • ☐ Keep read-only access to the old system for at least 90 days.

First 30 days

  • ☐ Confirm renewal notices are generating on schedule.
  • ☐ Confirm late fees and recurring charges posted correctly on the first rent cycle.
  • ☐ Check that lead follow-up times didn’t slip.
  • ☐ Hold a 15-minute weekly check-in with super users to collect problems.
  • ☐ Rerun the reports from your “before you sign” list and confirm each one works.
  • ☐ Close the old contract once data is fully exported and verified.

The one question that matters

Who owns the operation after the vendor’s implementation team goes home? If nobody has that answer, plan the project before you pick the software.